Syria Details $199 Million Highway Rehabilitation Project

Work to repair road defects on the Ariha-Latakia Highway (M10), July 20, 2026. (Ministry of Transport/Facebook)

Work to repair road defects on the Ariha-Latakia Highway (M10), July 20, 2026. (Ministry of Transport/Facebook)

A A A

Syria is preparing to rehabilitate several major roads connecting the north and south of the country, following the completion of contract procedures for a project worth more than $198 million.

Moaz Najjar, director of the General Establishment for Road Transport, told Enab Baladi that contract procedures for rehabilitating key sections of the country’s central and strategic road network had been finalized. The project covers the Damascus-Homs and Homs-Aleppo highways, the Saraqib-Idlib road link, and the Nasib-Damascus highway, at a total cost of $198.99 million, funded by the state budget.

The project is part of preparations to implement a three-year plan to develop Syria’s road infrastructure, announced by the Ministry of Transport on October 23.

Transport Minister Yarub Badr previously discussed technical and logistical preparations and the steps needed to begin implementation during a meeting with Mohammed Sultan Al Jaber, chairman of Qatar’s Al Jaber Group, and Naji Berri, director of Loubar Trading Company, following the approval of a consortium formed by the two companies.

Four Major Routes

According to Najjar, the project covers four main routes extending over a total of 463 kilometers, forming a key part of the country’s central road network and connecting southern, central and northern governorates:

  • Nasib-Damascus Highway: 100 kilometers.
  • Damascus-Homs Highway: 168 kilometers.
  • Homs-Aleppo Highway: 195 kilometers.
  • Saraqib-Idlib road link.

These routes have four traffic lanes and are among the country’s busiest roads for passenger travel, freight transport and movement between governorates.

How Is the Contract Value Distributed?

Najjar said the project’s total value is $198,994,861, distributed across three main contracts:

  • Nasib-Damascus Highway: $46,791,756.
  • Damascus-Homs Highway: $68,840,000.
  • Homs-Aleppo Highway and Saraqib-Idlib road link: $83,363,105.

Rehabilitation Work

Najjar explained that the project involves rehabilitating existing roads and improving traffic safety through a range of technical and service-related works, including:

  • Removing damaged asphalt layers, laying new asphalt and repairing damaged sections.
  • Rehabilitating existing drainage culverts and constructing new ones where necessary.
  • Maintaining stormwater drainage systems and clearing ditches and drainage grates.
  • Cleaning central medians and planting them with various types of trees.
  • Implementing road safety measures, including road markings, barriers, signs and traffic signals.
  • Maintaining existing road lighting systems and installing new solar-powered lighting poles.

He added that all work would be carried out in accordance with the ministry’s approved technical standards and specifications, as well as the specific contractual requirements of each project.

Implementation Timelines

The contracts have implementation periods ranging from 400 to 500 days, according to Najjar, with the timelines distributed as follows:

  • Nasib-Damascus Highway: 400 days. The notice to proceed for the first section was issued on October 8.
  • Damascus-Homs Highway: 500 days.
  • Homs-Aleppo Highway and Saraqib-Idlib road link: 500 days.

Najjar noted that contract-signing procedures are still being completed for some sections ahead of implementation.

Syrian-Qatari Consortium to Carry Out the Project

Najjar explained that the consortium comprising Loubar Trading Company and Qatar’s Al Jaber Group was selected through a domestic and international request for proposals.

He said Loubar Trading Company holds an excellent-grade classification issued by the Ministry of Public Works and Housing, while Qatar’s Al Jaber Group is an established regional company operating in the contracting sector.

Najjar added that supervision of the projects had been assigned to IDS Consulting following a technical and financial evaluation of submitted bids. However, the supervision contract is still undergoing signing and approval procedures.

Quality Guarantees

Regarding measures to ensure that the companies complete the work to a high standard and within the agreed deadlines, Najjar said the contracts include technical and financial guarantees.

These include performance guarantee deductions equivalent to 5% of the contract value, as well as penalties and deductions in cases of delays or failure to comply with approved technical specifications.

To maintain traffic flow during construction, Najjar said a flexible traffic management plan would be adopted, allowing work to proceed on individual sections or lanes, with temporary diversions equipped with the necessary road safety measures.

Expected Benefits for Transport and Trade

The director of the General Establishment for Road Transport expects the project, once completed, to reduce travel times between major governorates and lower transportation, freight and logistics costs.

He said these improvements could benefit domestic trade and affect commodity prices, while also improving road safety and reducing accidents on major international highways.

The project follows years of varying levels of damage to large sections of Syria’s road network as a result of the war, accompanied by declining routine maintenance and increasing traffic loads on many major routes.

النسخة العربية من المقال

Related Articles

  1. Rehabilitation of the Nassib-Damascus Highway, Agreement Signed After Machinery Arrives
  2. Damascus-Nassib Highway Work Begins After $2M Cut
  3. Infrastructure “gaps” drive up traffic accidents in Syria
  4. Qatari Firm Wins $150M al-Busayrah-al-Tanf Road Project

Propaganda distorts the truth and prolongs the war..

Syria needs free media.. We need your support to stay independent..

Support Enab Baladi..

$1 a month makes a difference..

Click here to support